What's being done
A new 3/4-mile (4,035-foot) bridge will be built over
Black Narrows and Lewis Creek Channel. The bridge will
provide motorists with better access to the Town of
Chincoteague. A 729-foot connector bridge will be built
linking the new bridge to Marsh Island.
The new bridge will maintain a single lane of traffic in
each direction, divided by a double line.
Features
The project technically calls for the construction of
two new bridges that intersect one another over Black
Narrows.
The primary bridge will begin on the west side of Black
Narrows at Route 175 and span north to connect with
Maddox Boulevard in Chincoteague at the Main Street
intersection. The portion of the new span that crosses
over Lewis Creek Channel will be a drawbridge.
Motorists will be able to access Marsh Island from the
new bridge by using a second bridge called the Marsh
Island Connector. The Marsh Island Connector will exit
onto Marsh Island at the same location as the existing
Black Narrows Bridge.
The new bridges will maintain a single lane of traffic
in each direction, divided by a double line. The
existing Black Narrows and Chincoteague Channel bridges
will be demolished following construction.
Benefits
Reduces traffic congestion in downtown Chincoteague
Allows boats better channel access
Reduces the number of necessary bridge openings
Increases safety by providing wider lanes and shoulders
Improves industrial access by allowing VDOT to consider
permits for overweight loads
Project Updates
The contract was awarded to American Bridge in
January of 2007 and the scheduled completion date is
November 9, 2009.
Why is this road being
built?
The two existing bridges that this project will replace
were built in 1939 and 1940. While they remain safe,
their age has led to a certain degree of deterioration
and subsequently, costly repairs. Additionally, the
bridges are narrower than current standards dictate.
Why was this project
design chosen over alternatives?
The connection to Main Street at Maddox Boulevard
facilitates direct access to and from the largest
commercial area on Chincoteague Island. It also services
most of the traffic going to and from Assateague Island
Downtown traffic congestion will decrease in the
vicinity of the existing Route 175 intersection at Main
Street in the vicinity of the fire station
The drawbridge on this alignment is the shortest among
all alignments that were studied
The new drawbridge will require fewer bridge openings
due to its northern location
It improves maintenance of traffic and minimizes
disruption of traffic during construction
The Chincoteague Town Council and the Accomack County
Board of Supervisors each adopted a resolution
supporting the Maddox Boulevard Alignment
Contact Information
Leah
Bott, 757-925-1515
Contractor
American Bridge
Cost
$68.7 million
Completion Date
November 2009
News paper article (Eastern Shore News)
All photographs and text
on this page are courtesy of the Virginia Department of
Transportation.